Another project is nearly finished!

Radlett 3 projectOne of HEB’s amazing projects based in Radlett, Hertfordshire will be finished within 7 weeks. Our team is exceptionally busy on the first floor of this great property. 

We have started this project in 2015. Firstly, we have implemented amendments in the constructional steel structure. Later, we have added double storey extensions, built a new roof and started a full internal renovation.

Most of the rooms have been already decorated and the doors have been fitted in. All of the bathrooms have been beautifully tiled and are ready for a finishing touch. During next month, we will be implementing a sliding wall between lounge area and the kitchen, then fitting the staircase, carpets and installing all of the remaining fittings. Last week is reserved for refreshing the front elevation.

To view more photos from that project, visit our ‘current projects‘ section.